Mumbai Concreting work on Gokhale Road bridge done

After declaring February 25 as the new deadline for the Gokhale bridge at Andheri, the Brihanmumbai Municipal Corporation (BMC) completed concreting the bridge on Monday. The curing period for the concrete is three weeks, and remaining work, including lighting, signage, lane marking, will be done simultaneously to complete it by February 23.  Meanwhile, in a follow-up letter to the BMC, residents raised the issue of the condition of the unused newly built Teli Gali flyover and the unfinished work…